Short Answer: A 5-kilowatt solar power plant connected to the grid generates approximately 46 to 52 million Iranian tomans in gross annual revenue in the year 1405. After accounting for the construction cost of 350 to 400 million tomans, your investment will be recovered within 4.5 to 5 years. After this period, the electricity sales revenue over the remaining 20-year contract will constitute your net profit.

What is the actual construction cost?

According to the Director of the Economic Review Office of SABA, the construction cost of a 5-kilowatt solar power plant connected to the grid in the current year is between 350 and 400 million tomans. This range depends on the type of equipment (panel brand, inverter, and structure) and installation conditions. Please note that this figure is for a grid-connected (On-Grid) power plant; if you wish to use the generated electricity for personal consumption and store it during nighttime hours, you must also add the battery cost to this amount, which we discuss in the second article.

How is annual income calculated?

Three main variables are involved in calculating income: plant capacity (5 kilowatts), average effective daylight hours in Iran (approximately 4.8 hours per day), and the guaranteed electricity purchase rate. The base guaranteed electricity purchase rate for residential solar power plants in the year 1405 is set at 5,845 tomans per kilowatt-hour.

With these figures, the annual production of a 5-kilowatt power plant is estimated at approximately 8,800 kilowatt-hours. Multiplying this number by the guaranteed purchase rate yields an annual gross income of approximately 51.5 million tomans. Some calculations, considering a more conservative return rate, estimate this figure at approximately 46.8 million tomans in the first year. The difference between these two figures arises from different assumptions regarding effective daylight hours and system losses.

Capital Recovery: 4.5 to 5 Years

If we assume the construction cost to be 375 million tomans (the average of the 350 to 400 million range) and the annual income to be 50 million tomans, the capital recovery period appears to be approximately 7.5 years. However, official SABA calculations, considering annual adjustment of the guaranteed electricity purchase rate (in line with inflation and exchange rate) and the possibility of selling electricity on the energy exchange, have announced the capital recovery period as 4.5 to 5 years. This means that the guaranteed purchase rate increases annually, and income in subsequent years will be higher than in the first year.

Important Note for Investors

The guaranteed electricity purchase contract is signed for a period of 20 years, and SABA is committed to purchasing your power plant’s electricity during this period. After the capital is recovered in the fifth year, the remaining 15 years of the contract will essentially constitute net profit. To begin, simply contact the experts at energyghp.com to select the best equipment combination (panels, inverters, and structures) based on your geographical location and available space.